NEW QUESTION # 21
Through which document programmes establish the context in which risks will be identified and assessed and responses planned and implemented?

  • A. Issue register
  • B. Risk register
  • C. Programme plan
  • D. Quality and assurance plan

Answer: B


NEW QUESTION # 22
Who approves Business Case?

  • A. Sponsoring Group
  • B. SRO
  • C. BCM
  • D. Programme Manager

Answer: B


NEW QUESTION # 23
Which of the following is not true about programme control?

  • A. Programme control justifies continuance of programme
  • B. Programme control minimizes impact of ambiguity
  • C. Programme control provides supporting activities to refine and improve delivery
  • D. Programme control defines reporting mechanism

Answer: D


NEW QUESTION # 24
Which of following is False?

  • A. Stakeholder profiles are created under stakeholder maps
  • B. Stakeholder profiles identifies and lists each stakeholder properties
  • C. Stakeholders can change during the lifecycle of programme
  • D. Instead of having individual stakeholders, it is better to divide them in suitable categories

Answer: A


NEW QUESTION # 25
For a programme that focuses on Political and societal change which scenario will lead to lower probability of success?

  • A. Change to current legislation
  • B. Changes to public service delivery model
  • C. Long term societal effects
  • D. New legislation reacting to societal trends

Answer: C


NEW QUESTION # 26
POTI model is part of which governance theme?

  • A. Business Case
  • B. Blueprint
  • C. Risk and issue management
  • D. Vision

Answer: B


NEW QUESTION # 27
Which of the following is Not one of MSP defined levels of stakeholder engagement?

  • A. Maintain Interest
  • B. Active Consultation
  • C. Keep informed
  • D. Formally Approve

Answer: D


NEW QUESTION # 28
Which of the following is NOT normally a characteristic of the Vision Statement?

  • A. Key benefits are implicit
  • B. It must be time dependent
  • C. It is short
  • D. It must describe a desirable future

Answer: B


NEW QUESTION # 29
Which of the following is an influencer type of stakeholder?

  • A. Business partner
  • B. Supplier
  • C. Management board
  • D. Media

Answer: D


NEW QUESTION # 30
Which document identifies appropriate milestones for benefit reviews?

  • A. Benefit realization plan
  • B. Information management plan
  • C. Business case
  • D. Quality and assurance plan

Answer: A


NEW QUESTION # 31
Which of following is input for 'managing the tranches'?

  • A. Approval to proceed
  • B. Assurance review reports
  • C. Programme preparation plan
  • D. Programme Brief

Answer: A


NEW QUESTION # 32
When it is found that an acceptable Business Case is not emerging, which of the following is NOT one of the normal options?

  • A. Design a Blueprint that is less ambitious
  • B. Close the Programme
  • C. Find a different approach to delivering the Blueprint
  • D. Seek further funding for the programme

Answer: D


NEW QUESTION # 33
Which of the following is not correct about 'Leading change'?

  • A. Appoint right people at right time
  • B. Create novel solutions to problems
  • C. Get approval from sponsoring group
  • D. Actively engage stakeholder

Answer: C


NEW QUESTION # 34
Which of below sentences describes Project Brief?

  • A. Control framework for programme
  • B. Control framework for projects
  • C. Describes purpose, cost, time, performance requirements and constraints of a project
  • D. List of all projects that will be part of programme

Answer: C


NEW QUESTION # 35
Which of following documents are parts of governance themes?

  • A. Business Case, Programme mandate
  • B. Blueprint, Requirement Specification
  • C. Blueprint, Vision, Quality management strategy
  • D. System and product specification

Answer: C


NEW QUESTION # 36
Which of following is not expected from senior leadership of programme?

  • A. Skilful in active management of cultural and people issues
  • B. Ability to create a compelling vision portraying a beneficial future
  • C. Good budgeting and resource allocation skills
  • D. Empowered decision making

Answer: C


NEW QUESTION # 37
Which of the following defines Dis-benefit?

  • A. A scenario that may bring profit or loss to programme
  • B. Measurable decline resulting from outcome perceived as negative
  • C. Measurable improvement resulting from outcome perceived as an advantage
  • D. Unplanned scenario that has happened and needs management intervention to reduce negative impact

Answer: B


NEW QUESTION # 38
In delivering the capability, which role is responsible for aligning projects with programme objectives?

  • A. SRO
  • B. Programme Office
  • C. Programme Manager
  • D. BCM

Answer: C


NEW QUESTION # 39
Which of the below is not a critical organizational element?

  • A. Recruitment Policy
  • B. Corporate strategy
  • C. Business as usual
  • D. Delivery mechanism for change

Answer: A


NEW QUESTION # 40
Which of the following is Not a core element of successful communication?

  • A. Message Clarity and consistency
  • B. Feedback Collection system
  • C. Identifying correct people to communicate
  • D. Stakeholder identification and analysis

Answer: C


NEW QUESTION # 41
......


Peoplecert MSP-Practitioner Exam Syllabus Topics:

TopicDetails
Topic 1
  • Programme Management: Develop expertise in programme management best practices, mastering principles, themes and processes to help organizations manage programmes effectively.
Topic 2
  • Quality Management: Understand quality assurance and control processes to ensure that programme deliverables and outcomes meet or exceed defined quality standards.
Topic 3
  • Resource Management: Learn how to allocate and optimize resources (human, financial and material) effectively, even in complex and changing environments, to achieve programme objectives.
Topic 4
  • Governance and Control: Gain an in-depth understanding of programme governance, including setting up and maintaining governance structures, accountability mechanisms and assurance processes to deliver programme success.
Topic 5
  • Problem Solving: Develop expertise in addressing complex programme management challenges and resolving issues efficiently and effectively.

 

Get 2025 Updated Free Peoplecert MSP-Practitioner Exam Questions and Answer: https://torrentvce.pdfdumps.com/MSP-Practitioner-valid-exam.html